Author Topic: Sorting Run order causes zones to run for wrong duration  (Read 8414 times)

snielson

  • Newbie
  • *
  • Posts: 2
    • View Profile
Sorting Run order causes zones to run for wrong duration
« on: September 13, 2014, 02:54:52 pm »
I changed the sort order by moving 10th zone up to the 7th position.  Then I created a new program and schedule.  The sprinklers didn't run in the same order that was displayed on the computer.  However, the durations followed.  So the zone I programmed to run for 3 minutes ran for 7.  The zone meant to run 7 ran 3.