Author Topic: Can not do manual runs after Canceling a run  (Read 10571 times)

auto_man

  • Newbie
  • *
  • Posts: 10
    • View Profile
Can not do manual runs after Canceling a run
« on: July 06, 2016, 07:07:27 am »
I have found that if I Cancel an active run, I can not start a Manual run until after the original run would have completed if it had not been canceled.   I'm running v2.03

There are times when I want to cancel an active run and then restart it, or start some other program.

bluespray_admin

  • Global Moderator
  • Sr. Member
  • *****
  • Posts: 327
    • View Profile
Re: Can not do manual runs after Canceling a run
« Reply #1 on: July 08, 2016, 07:35:35 pm »
When in stack mode, all schedules a stacked after another.  So your manual run is stacked.  You can get around it by setting Stack mode to "No".